Go Back  Offshoreonly.com > Boat Club Forums > TOPPS
The B.S. Thread >

The B.S. Thread

Notices

The B.S. Thread

Old 12-16-2008 | 01:47 PM
  #25311  
Registered
 
Joined: Mar 2005
Posts: 3,927
Likes: 2
From: Montgomery, Texas
Default

I just took a Big Andy and it smelled like Johnny Walker.....Is that bad?
joew. is offline  
Reply
Old 12-16-2008 | 02:57 PM
  #25312  
tomtbone1993's Avatar
Registered
 
Joined: Sep 2003
Posts: 15,491
Likes: 5
From: LAKE CONROE, TX
Default

12/15/2008 Ike Update

The project of designing and constructing the necessary repairs to the Lake Conroe dam following the damage incurred during Hurricane Ike is proceeding slightly ahead of schedule.

The original schedule was to complete engineering design in November, go out for bids in December, and then award a construction contract in January with a notice to proceed being issued in late-January or early-February. As outlined below, the project is currently running almost four weeks ahead of schedule.

On December 5, 2008, bids for the rock riprap repair project were received and opened. On Thursday, December 11th, the SJRA Board of Directors received the bid tabulation along with a presentation from SJRA staff and engineers with Freese & Nichols, Inc., recommending a contractor. The SJRA Board voted to award the construction contract to Rebel Contractors, Inc., based in Willis, Texas. Rebel’s bid was $978,268.50. It is anticipated that the cost of the repair will be eligible for at least 75 percent FEMA reimbursement.

The new schedule is to issue a notice to proceed in the first week of January. The contract allows 90 days for substantial completion of the project.

Impacts on Lake Level

Based on the engineer’s recommendations, the SJRA has agreed to maintain the lake level at or below 200’ MSL, which is one foot below normal pool level and less than half of the amount that the lake was lowered following Hurricane Rita in 2005. This will be the target, maximum lake level during the construction period, meaning that the lake level during construction will most likely fluctuate between 199’ MSL and 200’ MSL depending on rainfall, evaporation, and construction requirements. However, the level could fluctuate lower if we enter an extended period of less-than-normal rainfall.

As of today (December 15, 2008), the lake is already a few inches below 200’ MSL, so depending on rainfall and evaporation, we may only have to lower a few additional inches in January.

This information regarding lake level is being provided to inform boat owners and lake area residents and businesses so that they can make any necessary arrangements with regard to activities on the lake. Although the proposed one to two feet of lowering is less than half of the impact experienced following Hurricane Rita, boaters are advised to use caution on the lake due to the increased risk of underwater obstacles.
tomtbone1993 is offline  
Reply
Old 12-16-2008 | 03:08 PM
  #25313  
wstultz's Avatar
Thread Starter
Social Distortion
20 Year Member
Gold Member
 
Joined: Sep 2004
Posts: 5,728
Likes: 6
From: Lake Conroe,Texas
Default

Originally Posted by tomtbone1993
12/15/2008 Ike Update

The project of designing and constructing the necessary repairs to the Lake Conroe dam following the damage incurred during Hurricane Ike is proceeding slightly ahead of schedule.

The original schedule was to complete engineering design in November, go out for bids in December, and then award a construction contract in January with a notice to proceed being issued in late-January or early-February. As outlined below, the project is currently running almost four weeks ahead of schedule.

On December 5, 2008, bids for the rock riprap repair project were received and opened. On Thursday, December 11th, the SJRA Board of Directors received the bid tabulation along with a presentation from SJRA staff and engineers with Freese & Nichols, Inc., recommending a contractor. The SJRA Board voted to award the construction contract to Rebel Contractors, Inc., based in Willis, Texas. Rebel’s bid was $978,268.50. It is anticipated that the cost of the repair will be eligible for at least 75 percent FEMA reimbursement.

The new schedule is to issue a notice to proceed in the first week of January. The contract allows 90 days for substantial completion of the project.

Impacts on Lake Level

Based on the engineer’s recommendations, the SJRA has agreed to maintain the lake level at or below 200’ MSL, which is one foot below normal pool level and less than half of the amount that the lake was lowered following Hurricane Rita in 2005. This will be the target, maximum lake level during the construction period, meaning that the lake level during construction will most likely fluctuate between 199’ MSL and 200’ MSL depending on rainfall, evaporation, and construction requirements. However, the level could fluctuate lower if we enter an extended period of less-than-normal rainfall.

As of today (December 15, 2008), the lake is already a few inches below 200’ MSL, so depending on rainfall and evaporation, we may only have to lower a few additional inches in January.

This information regarding lake level is being provided to inform boat owners and lake area residents and businesses so that they can make any necessary arrangements with regard to activities on the lake. Although the proposed one to two feet of lowering is less than half of the impact experienced following Hurricane Rita, boaters are advised to use caution on the lake due to the increased risk of underwater obstacles.
That is semi-good news.
wstultz is offline  
Reply
Old 12-16-2008 | 07:32 PM
  #25314  
wstultz's Avatar
Thread Starter
Social Distortion
20 Year Member
Gold Member
 
Joined: Sep 2004
Posts: 5,728
Likes: 6
From: Lake Conroe,Texas
Default

This thing looks like an algae sucking bottom feeder...

http://cgi.ebay.com/ebaymotors/Ultim...rQ5fMotorboats
wstultz is offline  
Reply
Old 12-16-2008 | 08:49 PM
  #25315  
Registered
 
Joined: Jun 2006
Posts: 14,914
Likes: 1
From: Lake Conroe, TX.
Default

Originally Posted by wstultz
This thing looks like an algae sucking bottom feeder...

http://cgi.ebay.com/ebaymotors/Ultim...rQ5fMotorboats
Cool
jeff1000man is offline  
Reply
Old 12-16-2008 | 09:08 PM
  #25316  
Registered
 
Joined: Jun 2006
Posts: 14,914
Likes: 1
From: Lake Conroe, TX.
Default

Wade

http://cgi.ebay.com/ebaymotors/_Powe...1%7C240%3A1318
jeff1000man is offline  
Reply
Old 12-16-2008 | 09:11 PM
  #25317  
Registered
 
Joined: Jun 2006
Posts: 14,914
Likes: 1
From: Lake Conroe, TX.
Default

Is this a 1998 or a 1989?

Looks older than a 98

http://cgi.ebay.com/ebaymotors/_Powe...1%7C240%3A1318
jeff1000man is offline  
Reply
Old 12-16-2008 | 09:25 PM
  #25318  
Registered
 
Joined: Jun 2006
Posts: 14,914
Likes: 1
From: Lake Conroe, TX.
Default

Lot of boat for the money

http://cgi.ebay.com/ebaymotors/_Powe...1%7C240%3A1308
jeff1000man is offline  
Reply
Old 12-16-2008 | 09:28 PM
  #25319  
Registered
 
Joined: Jun 2006
Posts: 14,914
Likes: 1
From: Lake Conroe, TX.
Default

Chris Craft with a cigarette sticker

http://cgi.ebay.com/ebaymotors/_Powe...1%7C240%3A1318
jeff1000man is offline  
Reply
Old 12-16-2008 | 09:50 PM
  #25320  
Registered
20 Year Member
 
Joined: Jan 2003
Posts: 439
Likes: 1
From: Atlanta, GA
Default

Originally Posted by jeff1000man
Friend of mines boat from the Tickfaw. I know and have the 411 on this boat if interested.
mba1620 is offline  
Reply

Contact Us - Archive - Advertising - Cookie Policy - Privacy Statement - Terms of Service

Copyright © 2026 MH Sub I, LLC dba Internet Brands. All rights reserved. Use of this site indicates your consent to the Terms of Use.