Default $11M for harbor dredging (Michigan)

From the Detroit Free Press


http://www.freep.com/article/2013020...ichigan-harbor


TRAVERSE CITY — Gov. Rick Snyder will call for spending $11 million this year to dredge Michigan harbors...
Need4SpeedGTCS is offline  
Reply
Old 02-03-2013 | 09:22 AM
  #2  
Registered
 
Joined: Sep 2007
Posts: 2,568
Likes: 0
From: Gaylord, Mi
Default

Very good news
drpete3 is offline  
Reply
Old 02-03-2013 | 10:06 AM
  #3  
Registered
15 Year Member
 
Joined: Jul 2009
Posts: 1,407
Likes: 3
From: Bay City, MI
Default

Good news but 11 mil doesn't go very far dredging.
hotjava66 is offline  
Reply
Old 02-03-2013 | 11:13 AM
  #4  
Registered User
 
Joined: Aug 2012
Posts: 614
Likes: 0
From: Charlotte Mi.
Default

Originally Posted by hotjava66
Good news but 11 mil doesn't go very far dredging.
Exactly, at least its a start though.
GTOKILLER is offline  
Reply
Old 02-03-2013 | 12:24 PM
  #5  
Registered
15 Year Member
 
Joined: Mar 2008
Posts: 3,615
Likes: 377
From: Traverse City MI
Default

Our Gov't is amazing.

lets steal $750 MILLION from the Ports import tax for "other crap" and then steal only $11mil from the "improvements for marine infrastructure" fund (breakwalls and boat ramps) and look like heros for only replacing 750 MIL with 11 MIL! All while hurting the marina's while they pretend to help.

Why not, they steal from Social Security, steal from the Lottery instead of using the money for schools, etc.

Embarrassing
offshorexcursion is offline  
Reply
Old 02-03-2013 | 12:51 PM
  #6  
Registered
 
Joined: Aug 2011
Posts: 1,696
Likes: 2
From: Metro Detroit
Default

Just to dredge the DYC it is 1.1 Million. They will start mid march and work 60 days 20 hours a day. They will remove 28k cubic yards.

The biggest cost is whether the spoils are contaminated....in a marina most times they will be....then the cost is multiplied by 3 or 4.
Pwraddr is offline  
Reply
Old 02-03-2013 | 01:33 PM
  #7  
Registered
15 Year Member
 
Joined: Jul 2009
Posts: 1,407
Likes: 3
From: Bay City, MI
Default

Ran into a fellow contractor a while back who used to do a lot of dredging work. Says even though there is a ton to do, none of the marinas or associations have the money to do it, or worse hire the work and then don't pay. He basically is not doing much of it anymore for those reasons.
hotjava66 is offline  
Reply
Old 02-03-2013 | 06:50 PM
  #8  
h2oboater's Avatar
Gold Member
20 Year Member
Gold Member
 
Joined: Dec 2003
Posts: 3,498
Likes: 64
From: NewBaltimore Mi
Default

Originally Posted by Pwraddr
Just to dredge the DYC it is 1.1 Million. They will start mid march and work 60 days 20 hours a day. They will remove 28k cubic yards.

The biggest cost is whether the spoils are contaminated....in a marina most times they will be....then the cost is multiplied by 3 or 4.
The Michigan DNR paper work I have says all dredging must be done by 4-15-2013. They may change that as So many permits need to be approved. We are trying to get our canal done { off the Salt River on Lake St Clair] only had 6 homes responded out of 100. Most must have wishful thinking that the water will just magically come up.

Last edited by h2oboater; 02-03-2013 at 06:53 PM.
h2oboater is offline  
Reply
Old 02-03-2013 | 07:08 PM
  #9  
Registered
 
Joined: Aug 2011
Posts: 1,696
Likes: 2
From: Metro Detroit
Default

Originally Posted by h2oboater
The Michigan DNR paper work I have says all dredging must be done by 4-15-2013. They may change that as So many permits need to be approved. We are trying to get our canal done { off the Salt River on Lake St Clair] only had 6 homes responded out of 100. Most must have wishful thinking that the water will just magically come up.
It's already a done deal, they are starting mid march. Hope it works out for you....water is definitely LOW!
Pwraddr is offline  
Reply
Old 02-04-2013 | 06:38 AM
  #10  
Registered
 
Joined: Apr 2011
Posts: 324
Likes: 0
From: Emmet, WI
Default

The article states they will be dredging 6 areas, Saginaw being one of the areas. I've boated the Bay City, Saginaw and Saginaw Bay area my whole life. (Grew up a block away from Wirt Sone Mix) What site in Saginaw would they be dredging? Saginaw being so far from the Bay you would think th that one of the many water starved marinas on the Saginaw Bay would be a much better choice. It would be nice to make a run to Au Gres for lunch but have not been in many years due to water level.

Last edited by Jason3603; 02-04-2013 at 06:42 AM.
Jason3603 is offline  